Sunday 8 July 2018

How To Calculate Shuttering Quantity

How To Calculate Shuttering Quantity:


Shuttering is an essential temporary structure in which the fresh concrete is poured for casting different members of a structure. The shuttering is removed when concrete achieves its desired strength. There are different materials used in making shuttering such as plywood (as shuttering plate) Nails, wooden battens, beam bottom plates, wooden ballies, shuttering oil etc. In this article, I am going to discuss how to calculate quantity of shuttering by using thumb rule.


What is Thumb rule?


Thumb rule is a fixed number determined by our professional experience and daily practice at site. By using thumb rule we get an approximate quantity which is nearly to the exact quantity. Let’s get started.

Calculate shuttering quantity for below given slab:

Type of shuttering – Wooden shuttering




The length of the slab = 50 feet.

The width of the slab = 30 feet.

Total covered area = Length x Width = %0  x 30 = 1500 sft.

The quantity of Shuttering Required:


1. Plywood:


Generally, the dimension of plywood used in regular construction is 8’x4′ and thickness is 12 mm.

So plywood required = Covered area x Thumb rule = 1500 x 0.02 = 30 no’s

2. Wooden Battens:


Standard dimension of wooden battens is 3″x3″

Wooden battens required = Covered area x Thumb rule = 1500 x 0.04 = 600 rft

rft means running feet, which is the total length of the material. We cut this total length as per our required size.

3. Nails:


Nails required = Covered area x Thumb rule = 1500 x 0.02 = 30 kg.

4. Beam Bottom Plates:


The thickness of beam bottom plate is 1.5″

Beam bottom plates required =  Covered area x Thumb rule = 1500 x 0.24 = 360 rft.

5. Wooden Ballies:


Wooden ballies required for beam = Beam bottom plate running feet x Thumb rule

= 360 x 0.5 = 180 no’s

Wooden ballies required for slab = Covered area x Thumb rule = 1500 x 0.16

= 1500 x 0.16 =240 no’s

6. MS Clamps:


MS Clamps required = Covered area x Thumb rule 1500 x 0.08 = 120 no’s

7. Shuttering Oil:


Shuttering oil required = Covered area x Thumb rule = 1500 x 0.006 = 9 liters

Note:

1. These are just approx quantity. To get exact quantity you need to get the exact dimension of members where the shuttering will be used.

2. The above thumb rules may vary with changing the dimension of shuttering plate etc.


How To Calculate Quantity Of Binding Wires For Steel Bars:


Binding wires are used to tie the steel bars. Besides estimating of steel quantity for different members it is also important to know the required amount of binding wires. So that we can order correct quantity of steel. In this article, I will discuss how to calculate quantity of binding wires.
Well, let me tell you one thing first, there is no such formula for calculating binding wires. Instead, we use some thumb rules as per construction industry.
The quantity of binding wires depends on the type of structure where it will be used and type of bar (diameter of bar length of bar).
As per thumb rules,

Requirement of binding wires for 1 quintal (100 kg) of steel reinforcement = 0.9 to 1.3 kg
Requirement of binding wires for 1 ton (1000 kg) of steel reinforcement = 9 to 13 kg
Thus, binding wire required for tying 1000 kg of 8 mm bars is about to 12 kg and for 28 mm or 32 mm bars it will be approximately 7 kg. Greater the diameter of the bar, lesser the quantity of binding wire.


Source :- www.dailycivil.com

No comments:

Post a Comment